Sunday, September 26, 2010

Blossom (Precinct 4) Bungalows Launch

The last phase of Garden Residence was launched this weekend, this is earmarked as Precinct 4 and is located at the north most area, next to Putrajaya Precinct 11.  These bungalows will have a standard land size of 60’ by 90’ but is being launched from 3.2 million onwards!  Why is it so much more expensive that the other bungalows in Garden Residence?  It will have a build up area of more than 7,700 sq ft and with an internal lift servicing the 4 floors.

Garden Residence Blossom Bungalow

The overall layout is quite standard for the ground floor, with 1 guest room and 1 utility/maid’s room.  The 1st and 2nd floors are very much the same layout, each with a master bedroom and 2 smaller rooms at the rear (with en-suite individual bathrooms) and the 3rd floor (roof) will have a “party” area with a large open air Jacuzzi.

Garden Residence Blossom Bungalow

As can be seen from the pictures, the show unit is being built currently.  It looks very large as compared to the other smaller bungalows.  We can’t wait for have a look at it when it is ready.

On the sales update, there are approximately 6 unit of 2 storey superlink, 3 units of 3 storey superlink, 5 units of semi-d (both types) and a whole lot more bungalows for sale.

Wednesday, September 8, 2010

Project Development Progress as of 8th September 2010

There aren’t much visible progress on site other than 3 major items.

  • Precinct 3’s piling work seems to be well on the way and would probably finish soon.  Precinct 3 is where the show units are at the moment.
  • Precinct 2, being on higher ground has a driveway entrance that can be quite grand as it goes uphill.  The retaining walls are ready.
  • The road that goes between Precinct 1 and Precinct 2 leading towards the bridge link near LimKokWing University is taking shape (picture below).

Garden Residence P1-P2 

Progress can be seen on Precinct 2 houses, where more Semi-Detached units are having their walls bricked.  Work on the 3 Storey Superlink is also progressing quickly now.

Garden Residence Superlink

The 2 Storey Superlink unit where work first started has had it’s roof structure completed and bricks being brought in to start on the walls.

Garden Residence 2SSL

Other news around Cyberjaya, AMD has taken one building at SME Technopreneur Park III and the road leading towards the south of Cyberjaya is near completion.  Expect the road to link to the south interchange that leads towards Pullman Putrajaya to be completed soon.

AMD @ SME III

Note that the road next to DELL is rather busy now with vehicles using that connection to get to AMD, KRU Studios and many of them towards HP.  HP staff have started to move in although officially, it will be after the Eid.

KRU Studios

Posted from: gardenresidence.blogspot.com